# XP and the cost of change

I have found myself drawing the classic cost of change graph a few
times recently so thought I would blog about it. The graph was popular
a few year ago in explaining the differences between and eXtream
Programming (XP) team cost and a waterfall team cost.  <img
src="https://www.grahambrooks.com/images/XP-Wall-Graph.png"
alt="XP Wall Graph.png" border="0" width="341" height="209"/>

The important thing to remember in interpreting the graph is that the
lifetime of a software system is typically far longer than the initial
development. Most systems spend much longer in ‘maintenance’ than they
ever did in ‘development’ so anything that can be done to make
maintenance (ongoing development) more effective has to make sense.

The XP premies is that by augmenting the codebase with automated tests
changes are easier to make later on. Developers can regression test
the code to make sure that they have not broken anything and that
their new tests also pass. This requires the same if not more
discipline than the original development.

It is also important that refactoring be part of this ‘maintenance
development’ without it the system will degrade, making it more
difficult to effect changes.  A couple of years ago I was fortunate to
work with a team developing a web application. Nothing special perhaps
but the combination of background and skills for this project turned
out to rather special. After the first release which was made under
extreme time pressures new features were needed and added.
 
The key difference was the aggressive and determined pursuit of simple
elegant code present in all of the team. At around the second release
it was felt that ‘the code just wrote itself’. The code seemed to
support the addition of new features and productivity improved
dramatically.

Some time later it was decided that ongoing development be moved
offshore.

As a lead developer this can be a troubling time but as part of the
handover myself and another senior developer were asked to take the
project offshore to ensure a smooth transition.

And this is where things got interesting. The team were delighted with
the code and were keen to get started. Some scheduling conflicts meant
that they could do a development iteration (1 week) and work on some
of the backlog before envisioning the next major release.

That week was great fun with many whiteboard discussions about the
principles underlying the architecture and the design.

After the development iteration the team felt confident in moving
forward. That confidence proved to be true. The rate of changed
increased and the client was delighted with the results.

If you are reading this and were part of the onshore or offshore team
then thank you for such a fun time and wonderful code.

P.S. And yes I remember how hard the project was too.